Cambridge has been home to AstraZeneca's Discovery Centre since 2021 RUYING YANG FOR VARSITY

AstraZeneca has launched a £32 million High Court claim against a fire consultancy for “failing to comply with its duties” and causing “widespread defects” in the construction of its Cambridge-based facility, according to The Times

The claim was made against International Fire Consultants (IFC), a Cheltenham-based fire engineering consultancy. IFC was hired to work under construction manager Skanska on the development of AstraZeneca’s Discovery Centre, which is located in Cambridge's Biomedical Campus.

In 2013, AstraZeneca revealed their plans to relocate their global headquarters to Cambridge. Since then, the multinational pharmaceutical giant has collaborated closely with the University of Cambridge. The partnership has produced over 260 university grants, has spanned over 30 departments, and employed over 125 senior researchers and over 160 PhD students.

AstraZeneca's Discovery Centre was originally due for completion in 2016, however, the unveiling was delayed until 2021. After the unveiling, the building’s full opening was delayed even further due to an accidental electrical fire in December 2022.

The project was originally capped at £330 million, however, AstraZeneca ended up spending a total of £1 billion on development, venturing £670 million over budget.

AstraZeneca has previously attributed the project’s severe delays and unexpected budget changes on the complexity of the build, construction cost inflation, and their investment in new technologies and equipment.

The company also previously attributed the rise in costs to a shift in management. In 2018, Mace replaced Skanska as the project’s construction manager, also taking over as IFC's supervisor. AstraZeneca stated that a project review performed by Mace introduced factors which also altered the project's budget.

On top of these previous attributions, AstraZeneca alleges in their recent claim that the project's “critical delay” was mostly caused by IFC’s faulty work.

AstraZeneca’s claim alleges that “widespread defects were identified in relation to the fire dampers, smoke dampers, insulation and ductwork after they were installed”.


READ MORE

Mountain View

AstraZeneca pulls £200 million in funding for Cambridge research site

They go on to state that although IFC identified several of these defects during a re-inspection of the building in 2021,  the consultancy failed to do so during the preliminary stages of build, which was a liability.

AstraZeneca stated that between 2021 and 2023, the remediation work they carried out to address the defects cost them over £31.7 million.

IFC has filed a defence against the allegations. Their filing calls AstraZeneca’s claim “misconceived and incorrect”. It also suggests a possible motive for the false claim, referencing how AstraZeneca “entered into a final account settlement with Skanska that released it from its liability for latent defects in its works”.

AstraZeneca has issued a court reply to IFC’s defence, rejecting it and calling it “legally incoherent”.

This dispute follows the recent cancellation of AstraZeneca’s £200 million expansion project. The expansion of the Cambridge headquarters was anticipated to open up 1,000 new jobs, however the funding was suddenly pulled this past September.